<?xml version="1.0" encoding="utf-8" standalone="yes"?><rss version="2.0" xmlns:atom="http://www.w3.org/2005/Atom"><channel><title>Estimating on Duly Noted</title><link>https://noted.jsrowe.com/tags/estimating/</link><description>Recent content in Estimating on Duly Noted</description><generator>Hugo</generator><language>en-us</language><lastBuildDate>Thu, 18 Jun 2026 02:18:27 +0000</lastBuildDate><atom:link href="https://noted.jsrowe.com/tags/estimating/feed.xml" rel="self" type="application/rss+xml"/><item><title>why man-hour estimates fails to scale with a team</title><link>https://noted.jsrowe.com/why-man-hour-estimates-fails-to-scale-with-a-team/</link><pubDate>Thu, 18 Jun 2026 02:18:27 +0000</pubDate><guid>https://noted.jsrowe.com/why-man-hour-estimates-fails-to-scale-with-a-team/</guid><description>&lt;blockquote&gt;
&lt;p&gt;Imagine four independent tasks, each estimated at 40 hours (one week). The team starts working on all of them on Monday, expecting everything to be finished by Friday. But there are only two developers, and each can only focus on one task at a time. By the end of the week, only two tasks are finished. Pure time estimates completely ignore team capacity and parallelization constraints. While a two-person startup might mentally juggle this discrepancy, once the team grows bigger, relying on simple time estimates becomes an administrative nightmare.&lt;/p&gt;</description></item></channel></rss>